Sycamore Township 2021 Road Improvement Program
It has been a very busy year so far for roadway construction within the Township.  To date, our contractors have paved over eight (8) miles of roadway and have constructed over 1,400 feet of concrete curb.  The following roads and subdivisions have been completed:  Pinecove Court, McCauly Woods Subdivision and Trowbridge Subdivision in Northern Sycamore Township: Concord Hills Subdivision, Heitmeyer Farms Subdivision and Holiday Acres Subdivision in Kenwood; and Applewood Drive, Valerie Court, Blossom Drive and Winesap Court in Dillonvale Subdivision. The paving of the entire parking lot at Bechtold Park has also been completed.

The contractor will continue to work in Dillonvale Subdivision on the following roads: Donna Lane, Wexford Avenue, Belfast Avenue, Limerick Avenue, Darnell Avenue, Dublin Court, Wicklow Avenue, Mantel Avenue, Eldora Drive, Cresthaven Lane, Sedwich Drive, Rolling Lane, Estermarie Drive, Jud Drive and Huddleston Drive.  The Township’s 2021 Road Improvement Program is scheduled to be finished by the end of September.

 

Kugler Mill Road Improvements
Phase 1 (Blue Ash Road to Kenwood Road): The contractor has completed the installation of the new water main, storm sewers, concrete curb, curb ramps, and concrete sidewalk on the north side, driveway adjustments, a roadway profile adjustment at Kenwood Road and the milling of the existing pavement.

The contractor is scheduled to begin the construction of the roadway base pavement on July 14.  That work will be followed by the construction of the asphalt leveling and surface courses, pavement markings, topsoil and seeding of disturbed areas, and at the intersection of Kenwood Road, new mast arm traffic signal poles and traffic signal heads.

Phase 2 (Kenwood Road to Montgomery Road):  The contactor is scheduled to begin work on this section of Kugler Mill Road in August. The project is scheduled to be completed by the end of 2021.

 

Larchview Drive and Plainfield Road Improvements
The improvements to Larchview Drive (Eldora Drive to Plainfield Road) include: the construction of a new water main, storm sewer, roof drain collector lines, concrete rolled curb, curb ramps, reconstruction of sidewalk on the north side and complete reconstruction of the pavement. The improvements to Plainfield Road (Donna Lane to Larchview Drive) include: the construction of a water main, curb repair, curb ramps, asphalt pavement, new mast arm traffic signal poles and traffic signal heads at the intersections of Donna/Myrtle and at Larchview and new pavement markings, as per the road diet plans. The proposed schedule for the project is as follows: the project will be bid in August of 2021, Utility Construction to begin in September, Water Main Construction to begin in the Fall of 2021, Roadway Reconstruction to begin in February of 2022.  The project is scheduled to be finished in late 2022.

Road Work Ahead SignDillonvale Culvert Improvements
This project includes culvert improvements at the following locations:

3946 & 3945 Mantell

3904 & 3905 Mantell

8589 & 8596 Wicklow

The improvements will consist of modifications to the existing headwalls, construction of new headwalls and grading work.  The project will be bid in August of 2021 and completed by December of 2021.

Donegal Drive Culvert Improvements
This project includes culvert improvement at the following location:

North Side of the Culvert at the intersection of Gwilada and Donegal.

The improvements will consist of modifications to the existing headwalls, construction of new headwalls and grading work.  The project will be bid in Fall of 2021 and completed by Spring of 2022.

Kenwood Meadows – Greater Cincinnati Water Works Project
Construction is expected to begin on or around February 22, 2021.

Construction is to be complete on or around October 20, 2021.

The Contractor will normally be working Monday through Friday 7:00 a.m. to 6:00 p.m.

The Contractor will maintain traffic access for residents, emergency vehicles and school buses at all times.

Contact Information: Greater Cincinnati Water Works – Mark Niehe (513) 591-7870, or Jon Hunseder (513) 702-4012.

Contact Information: Sycamore Township – Tracy Kellums (513) 792-7257 or Steve Reutelshofer (513) 792-7258.