06/29/2021 Progress Update:

The following roads and subdivisions have been completed:  Pinecove Court, McCauly Woods Subdivision, and Trowbridge Subdivision in Northern Sycamore Township; Concord Hills Subdivision, Heitmeyer Subdivision and Holiday Acres Subdivision in the Kenwood area; and Applewood, Valerie, Blossom and Winesap in Dillonvale Subdivision. The paving of Bechtold Park has also been completed.

Dillonvale curb work began on June 3rd and will continue through the end of July. The milling of the asphalt pavement on the following streets in Dillonvale: Donna, Wexford, Belfast, Limerick, Darnell, Dublin, Wicklow, Mantell, Donegal, Eldora, Cresthaven, Sedgewick, Rolling, Estermarie, Jud and Huddleston will begin after completion of the curb work. This will be followed by full depth pavement repairs,  the installation of FiberMat, and the final asphalt pavement.

If you have any questions or concerns about the 2021 Road Program, please contact Superintendent/Assistant Administrator Tracy Kellums at tkellums@sycamoretownship.org or 513-792-7257 or Design Technician Steve Reutelshofer at sreutelshofer@sycamoretownship.org or 513-792-7258.


2021 Road Program Project Overview:

The Township has begun a very extensive repaving and curb program in the subdivisions this year, with paving and curb work being done in Kenwood, Dillonvale and the northern part of the Township. This project will cover approximately 10.25 miles of roadway, which is about 20% of the Township’s total mileage. The John R Jurgensen Company was awarded the contract for an amount of $3,130,375.60. This is another project being paid for out of Tax Increment Financing (TIF) funds that are generated by commercial development in the Township, which allows the Township to keep your taxes low and not come to you, our residents, for a road levy.

Curb Program Letter to Residents Asphalt Project Letter to Residents