The Contractor is making good progress on the first phase of construction, which entails installing a new watermain from Applewood Drive to Plainfield Road and then from Applewood Drive to Eldora Drive.

The Contractor has completed the watermain from Applewood Drive to Plainfield Road and is currently installing a new watermain on Plainfield Road from Larchview Drive to Rossplain Road. After the watermain is installed on that section of Plainfield, the contractor will then return to Larchview Drive to begin work on the watermain from Applewood Drive to Eldora Drive. After the watermain is installed, the contractor will then begin to install new service laterals to each residence.

The maintenance of traffic is as follows: Larchview Drive is Closed between Mantell Drive and Plainfield Road.  Only residents that have a driveway on Larchview Drive, within the Construction Limits, are permitted on Larchview.  All other residents, please follow the posted detour for Larchview Drive.  Traffic is maintained on Plainfield Road.

Various phases of construction will continue along Larchview Drive until the Fall of 2022.

A second crew, from the Contractor, has begun replacing the watermain on the south end of Plainfield Road from Donna Lane to Kugler Mill Road.  The watermain that is being replaced has been in service since 1949. This section of the watermain replacement is expected to be completed by mid-February. This crew will then proceed north of Sycamore Road to replace another section of watermain along Plainfield Road.

Various phases of construction will continue along Plainfield Road until the Fall of 2022.

We appreciate everyone’s cooperation and patience during this time.  If you have any questions, please call our project inspector, Mark Homan at (513) 617-1731.