2024 Road Improvement Program

Construction is scheduled to begin this summer and be completed by the fall with an estimated cost of $764,524.25.

Sycamore Township Project Inspector Tony Perkins will oversee all aspects of the work done during these projects and assist our residents with any questions or concerns that may arise. Tony may be reached at 513-792-7247 or [email protected].

 2024 Reclamite Project Road List

Contractor: Pavement Technology

Charteroak Drive
Donegal Drive (Wicklow to West CDS)
Donna Lane (Plainfield to Estermarie)
Estermarie Drive (Donna to Mantell)
Guam Drive
Gwilada Drive
Hermitage Lane
Highton Court
Ivybrook Court
Jeffrey Drive
Langhorst Drive
Whitechapel Drive

2024 Pavement Repairs Project Road List

Contractor: Rack and Ballauer Excavation

1st Avenue
2nd Avenue
3rd Avenue
4th Avenue
5th Avenue
6th Avenue
7th Avenue
Park Street
Cincinnati Avenue
Evans Street
Gideon Lane

2024 Curb Repairs Project Road List

Contractor: Adleta Construction

Edington Drive
Ellington Court
Gideon Lane
Northlake Drive

2024 Sidewalk Repairs Project Road List

Contractor: Prus Construction

Autumnwind Drive
Bearcreek Drive
Buckland Drive
Cedarbreaks Lane
Fawncreek Drive
Fieldsted Drive
Stillwind Drive
Timberbreak Drive